Chart with ProcessAtEnd = True

Stimulsoft Reports.NET discussion
Post Reply
ikirck
Posts: 23
Joined: Fri Aug 25, 2006 4:25 am

Chart with ProcessAtEnd = True

Post by ikirck »

Hello,

I'm trying to use a chart with the ProcessAtEnd property set to true. However, a chart with this property enabled is never printed, regardless of where in the report it is situated - I tried both the title- and the summary band.

If I set the property to false, the same chart is printed all right - but without the data I need, of course.
Edward
Posts: 2913
Joined: Fri Jun 09, 2006 4:02 am

Chart with ProcessAtEnd = True

Post by Edward »

Now we look into the issue. We will inform you in this topic about the results.

Thank you.
Edward
Posts: 2913
Joined: Fri Jun 09, 2006 4:02 am

Chart with ProcessAtEnd = True

Post by Edward »

Fixed.

Will be available in the build from February, 9.

Thank you.
Post Reply