Gantt graph date range

Stimulsoft Reports.NET discussion
Post Reply
StixStax
Posts: 46
Joined: Wed Aug 12, 2015 9:41 am

Gantt graph date range

Post by StixStax »

For some reason I allways get a date range starting form 12.1899 (x-axis), although all values of the date coulmn start in 2015.I tested all values on a databand and couldn't find a date in 1899. Is there a way to fix this issue? I uploaded a screenshot of the graph.
Attachments
date_issue.png
date_issue.png (10.2 KiB) Viewed 2753 times
HighAley
Posts: 8430
Joined: Wed Jun 08, 2011 7:40 am
Location: Stimulsoft Office

Re: Gantt graph date range

Post by HighAley »

Hello.

Sorry, but we couldn't reproduce your issue.
Could you specify what version you use?
Please, try to set the Start From Zero property of the X Axis to False.

Thank you.
StixStax
Posts: 46
Joined: Wed Aug 12, 2015 9:41 am

Re: Gantt graph date range

Post by StixStax »

Thank for replying so fast Aleksey. I can't find the property Start from Zero. Would you mind posting a screenshot?
HighAley
Posts: 8430
Joined: Wed Jun 08, 2011 7:40 am
Location: Stimulsoft Office

Re: Gantt graph date range

Post by HighAley »

Hello.

You could find this property on the attached image.
StartFromZero.png
StartFromZero.png (36.22 KiB) Viewed 2745 times
Thank you.
StixStax
Posts: 46
Joined: Wed Aug 12, 2015 9:41 am

Re: Gantt graph date range

Post by StixStax »

Perfect. Solved my issue. Thanks so much
StixStax
Posts: 46
Joined: Wed Aug 12, 2015 9:41 am

Re: Gantt graph date range

Post by StixStax »

I'm trying to show the work hours for one day (24 h), but StimulSoft somehow automatically sets the range for 10 days. I'm using Version 2012.1.1300 (3rd April 2012). In your previous post I saw that in the new Stimulsoft Version you can set a Date Time step. Is this also possible in my version ?
Attachments
time_issue.png
time_issue.png (23.02 KiB) Viewed 2735 times
Last edited by StixStax on Wed Aug 19, 2015 7:21 am, edited 1 time in total.
HighAley
Posts: 8430
Joined: Wed Jun 08, 2011 7:40 am
Location: Stimulsoft Office

Re: Gantt graph date range

Post by HighAley »

Hello.
StixStax wrote:In your previous post I saw that in the new Stimulsoft Version you can set a Date Time step. Is this also possible in my version ?
Unfortunately, this feature was added much later.
Please, try our latest release.

Thank you.
Post Reply